Our Services

Our Services

July 18, 2024

Supreme Court of Appeal Rules on Binding Nature of Expert Report in Oil Metering Dispute


A discussion of
Krohne (Pty) Ltd v Strategic Fuel Fund Association (476/2023) [2024] ZASCA 99 (14 June 2024)

Introduction

This article discusses a legal dispute involving the accuracy of an oil metering system supplied by Krohne (Pty) Ltd (the appellant) to the Strategic Fuel Fund Association (the respondent). The case highlights the contractual disagreements, arbitration proceedings, and subsequent court rulings concerning the payment owed to Krohne for their services. The Supreme Court of Appeal (SCA) ultimately overturned the Gauteng Division of the High Court's decision, emphasizing the binding nature of the expert report used to settle the dispute.

FACTS OF THE CASE

The Agreement and Dispute

The Strategic Fuel Fund Association is responsible for managing South Africa's strategic energy reserves, which includes accurately measuring the volume of crude oil in its storage facilities. Krohne (Pty) Ltd won a tender to supply, install, and commission a metering system at the Saldanha Terminal. Their responsibilities included designing, calibrating, and installing the KOG metering system, along with all necessary electrical components.

The contract stipulated that payment would be made in stages, with the final 10% retained as a performance fee, payable upon satisfactory completion and certification of Krohne's work. A dispute arose when Krohne demanded this final payment, and the Strategic Fuel Fund Association claimed the metering system did not meet the agreed specifications.

Arbitration and Expert Report

To resolve the dispute, the parties agreed to arbitration. They settled on appointing an independent expert, SGS Gulf Limited (SGS), to assess the accuracy of the KOG metering system. The settlement agreement, endorsed by the arbitrator as an interim award, stipulated that the final report by SGS would determine the payment of the outstanding performance fee.

SGS eventually produced a final report, which Krohne interpreted as confirming that the metering system met the contractual specifications. Based on this interpretation, Krohne demanded the remaining payment. When the Strategic Fuel Fund Association refused, Krohne took the matter to the High Court to enforce the payment.

FINDINGS OF THE SUPREME COURT OF APPEAL

High Court Ruling

The High Court initially dismissed Krohne's application, upholding the Strategic Fuel Fund Association's point in limine. The court concluded that Krohne lacked a cause of action, interpreting the interim award and the SGS report as non-binding.

Supreme Court of Appeal Decision

The SCA found that the High Court had erred in its interpretation. The SCA emphasized that the issue at hand was whether the SGS report confirmed that the KOG metering system met the agreed specifications. The SCA ruled that the High Court should not have questioned the validity of the interim award or the binding nature of the expert report.

The SCA clarified that the parties had agreed in the interim award that the expert's final report would be binding. Therefore, Krohne's cause of action was legitimate, as it was based on the expert's findings. The SCA upheld the appeal, set aside the High Court's order, and remitted the matter back to the High Court for determination on the merits.

Conclusion

The Supreme Court of Appeal's decision underscores the importance of honouring settlement agreements and the binding nature of expert reports in contractual disputes. By remitting the case back to the High Court, the SCA ensured that the matter would be resolved based on the merits, rather than procedural technicalities. This ruling serves as a reminder of the legal principles governing arbitration and expert determinations in commercial contracts.

 

July 17, 2024

A Landlord’s Tacit Hypothec in Business Rescue: The Case of Ergomode and Sakhile


 Introduction to the Legal Principles

A landlord's tacit hypothec is a common law form of real security that allows landlords to claim movable property of tenants who are in rental arrears. However, landlords cannot enforce this hypothec through self-help; they must apply to a court for an order enforcing the hypothec over the tenant's property. This process, known as perfection, involves a sheriff attaching the tenant's property. Without perfection, the landlord's hypothec remains a theoretical remedy without legal enforceability.

The Facts of the Case

In the case of Ergomode (Pty) Ltd v Jordaan NO and Others, Ergomode entered into a lease agreement with Sakhile Contract Mining (Pty) Limited, where Sakhile operated a coal washing plant on Ergomode's property. By August 2020, Sakhile had accrued rental arrears of over R18.2 million. On October 23, 2020, Sakhile was placed under business rescue as per section 129(1) of the Companies Act 71 of 2008 (the Act). Shortly thereafter, business rescue practitioners (BRPs) were appointed. Ergomode submitted a claim for the rental arrears, but the BRPs only recognized ZAR12.8 million, citing damages caused by the removal of a filter press, a key component of the plant.

A business rescue plan was published on March 15, 2021, and adopted on March 30, 2021. The plan included relocating and refurbishing the plant. On February 22, 2022, the BRPs suspended the lease and initiated the removal of the plant. Ergomode then sought to perfect its landlord's hypothec in the High Court.

Findings of the Supreme Court of Appeal (SCA)

The SCA addressed several issues raised by Ergomode, primarily focusing on the perfection of the landlord’s hypothec.

  1. Perfection of the Hypothec:
    • Legal Moratorium: Under section 133 of the Act, a general moratorium on legal proceedings is imposed once a company is placed under business rescue. This means a landlord cannot perfect its hypothec without consent from the BRPs or the court.
    • Lack of Perfection: The SCA found that Ergomode’s hypothec was not perfected before Sakhile entered business rescue. Consequently, Ergomode’s application to perfect the hypothec during business rescue was denied due to the moratorium.
  2. Setting Aside the BRPs’ Determination:
    • Independent Creditor Status: Ergomode challenged the BRPs’ decision that it was not an independent creditor. However, section 145(6) requires such a review to be filed within five days of receiving notice of the determination. Ergomode failed to meet this deadline and did not object to the determination until after the business rescue plan was adopted. The SCA ruled against Ergomode, emphasizing its participation and voting in the creditor meetings.
  3. Validity of the Business Rescue Plan:
    • Timeframe for Plan Publication: Ergomode argued that the business rescue plan was invalid because it was adopted after the deadline for publication had passed without a valid extension. The SCA dismissed this argument, noting that extensions were granted by the creditors and Ergomode did not raise any objections during the adoption process. The SCA found that Ergomode's objection was a result of dissatisfaction with the plan's outcome rather than any procedural invalidity.

Conclusion

The SCA’s ruling in Ergomode (Pty) Ltd v Jordaan NO and Others reaffirms the legal principles surrounding a landlord’s tacit hypothec and the impact of business rescue proceedings. A landlord must perfect its hypothec before a tenant enters business rescue to enforce it as real security. The case highlights the importance of adhering to statutory timelines and procedures, and the necessity for landlords to act promptly and within the bounds of the law.